Saturday, April 24, 2010

Progress in late April

foundation and framing progress 

Timber frame ready is the goal by late Sunday





Thursday, April 1, 2010

Erection of the barn frame

We got a great start on the barn today. We had wind/snow spurts while we flew the roof sections on and way worse wind once we got them nailed/strapped.

Black shirt and red hat....Alexi G at work











Really glad Brady came by and tack welded the post bases to the base plate tops for the concrete piers.

Wednesday, March 31, 2010

House Permit is in hand, finally



The barn frame, the so called bents are now assembled and ready for erection...er...erecting




We have had a long wait and now we have the permit and a ton of stuff to do.
Barn erection starts today...stay tuned for photos, etc. We had enough dry weather to get into the site with the big crane....

Thursday, March 18, 2010

Poured concete today 3-18-10 w/Sand Hill Cranes heading north overhead

this is the frame for barn and house...should go up quickly....concrete piers for the barn was the mission today


65 today, major snows called for starting tonight through Friday night....calling for feet on the last day of winter
this hole is 8 ft deep and 30 inches in diameter....four of those and 14 holes 6 ft by 18 inches....it's just a barn